Choosing the right foundation system is crucial for structural integrity, cost efficiency, and overall success when planning a construction project. Two standard deep foundation solutions are bored piers and screw piling. Both have advantages, but their costs vary significantly depending on project requirements, soil conditions, and installation complexity.
Bored piers (or drilled shafts) are cylindrical concrete foundations installed by drilling holes into the ground, reinforcing them with steel, and filling them with concrete. They are commonly used in projects requiring high load-bearing capacity and stability.
Typically, it ranges between $350 – $800 per linear meter, depending on soil conditions and project complexity.
Screw piles are steel shafts with helical plates that are twisted into the ground like screws. They provide strong load-bearing support without the need for extensive excavation.
Generally, it ranges from $80 – $600 per linear meter, depending on pile size and soil conditions.
| Factor | Bored Piers | Screw Piling |
|---|---|---|
| Installation Time | Slower | Faster |
| Excavation | Required | Minimal |
| Material Costs | High (Concrete & Steel) | Moderate (Steel Piles) |
| Labour Costs | Higher | Lower |
| Site Disruption | Higher | Lower |
| Weather Impact | Delays Possible | Minimal Impact |
| Overall Cost | $350 – $800/m | $80 – $600/m |
If your project demands a high load-bearing and lateral load capacity, bored piers may be the best choice despite their higher cost. However, if speed, cost savings, and minimal site disruption are priorities, screw piling is often the more economical solution.
At Koble Constructions, we specialize in foundation solutions tailored to your specific needs. Contact us today for expert advice and a detailed cost estimate for your project.